Assemblage d'un joint de tuyau de type manchon
(1) Pre-installed the most important link of the pre-installation of the sleeve type pipe raccord affecte directement la fiabilité du joint. Des précurseurs spéciaux sont généralement nécessaires.Installations with small diameter can be pre-assembled on the bench vice. The specific approach is to use a raccord comme la matrice, l'écrou, le manchon de serrage peuvent être pressés contre le tuyau. Il existe principalement des manchons traversantsraccord, extrémité de type manchon à travers la tête de raccordement, tuyau à trois voies de type manchon raccordet d'autres types. De plus, il est found that even for a batch of goods from the same manufacturer, the depth of the conical hole on theraccord is often not the same, resulting in leakage, and this problem is often ignored. The correct way is to use what kind of raccord is used at one end of the pipe, and the corresponding fitting tail is pre-installed with the same type of raccord, so as to avoid leakage problems to the greatest extent. The end face of the pipe should be flush.
(2) After the pipe is sawed, it should be polished evenly on grinding wheel and other tools, and the burrs should be removed, cleaned and cleaned with high pressure air before use.
(3) Lors de la pré-installation, la coaxialité du tuyau et du raccord should be kept as far as possible. If the pipe is too deviation, it will also cause sealing failure.
(4) The pre-installed force should not be too ambassador that the inner edge of the sleeve is just embedded in the outer wall of the pipe, and the sleeve should not be obvious deformation. When connecting pipes, assemble according to the specified tightening force. The clamping force of the 6-1 sleeve is 64-1 15N, 16ф MMR 259N, ф18mm for 450N. If the jacket deformation is serious in pre-installation, the sealing effect will be lost.
It is forbidden to add sealant and other fillers. Some people in order to achieve better sealing effect, in the card sleeve coated with sealant, the sealant was rushed into the hydraulic system, resulting in hydraulic components Yin nihole blockage and other faults.
(3) When connecting the pipe, the pipe should have enough deformation allowance to avoid the pipe being subjected to tensile force.
(four) When connecting the pipeline, it should avoid being subjected to lateral force, which will cause loose sealing if the lateral force is too large.
(five) when connecting the pipeline, it should be good once and avoid multiple disassembly, otherwise it will make the sealing performance worse.
Folding card sleeve type piperaccord installation
(1) Le décapage des tuyaux exigé au chapitre 9 doit être effectué en priorité;
(2) Coupez le tuyau en fonction de la longueur requise avec une machine à scier ou une machine à couper les tuyaux spéciale et d'autres outils, il est absolument interdit de dissoudre le tuyau (comme l'oxycoupage) ou de couper la meule ; Enlevez les bavures à l'intérieur et à l'extérieur de l'extrémité du tuyau, les copeaux de métal et la saleté ; Enlevez l'agent antirouille et la saleté du tuyauraccord; En même temps pour assurer la rondeur du tuyau;
(3) l'écrou, le manchon a été placé dans le tuyau, le bord avant du manchon (petite extrémité) de la bouche du tuyau d'au moins 3 mm, puis le tuyau dans le raccordt body cone hole, top until;
(4) Serrez lentement l'écrou, tournez le tuyau jusqu'à ce qu'il ne bouge plus, puis serrez l'écrou 2/3 à 4/3 fois ;
(5) Ouvrez et vérifiez si la chemise a été coupée dans le tuyau et si la position est correcte. La veste n'est pas autorisée à avoir un mouvement axial, mais une petite rotation ;
(6) Serrez l'écrou après avoir réussi l'inspection.